A team has completed a couple of sprints for a new interface they are building for a client. The team is now ready to release the updates. What should the business analyst review?

The correct answer is B. Requirements traceability matrix. Before releasing sprint updates, the Business Analyst should review the Requirements Traceability Matrix (RTM) to verify that all documented requirements have been implemented and tested. The RTM links each requirement to its corresponding deliverables, test cases, and…

Business Analysis Frameworks

Question

A team has completed a couple of sprints for a new interface they are building for a client. The team is now ready to release the updates. What should the business analyst review?

Options

  • AWeighted ranking
  • BRequirements traceability matrix
  • CSystem interface table
  • DProduct backlog

How the community answered

(32 responses)
  • A
    3% (1)
  • B
    81% (26)
  • C
    3% (1)
  • D
    13% (4)

Explanation

Before releasing sprint updates, the Business Analyst should review the Requirements Traceability Matrix (RTM) to verify that all documented requirements have been implemented and tested. The RTM links each requirement to its corresponding deliverables, test cases, and acceptance criteria, ensuring nothing was missed or overlooked. The product backlog tracks remaining work, not completed requirement coverage. Weighted ranking and system interface tables serve different planning purposes.

Topics

#Requirements Traceability#Business Analyst Role#Release Verification#Agile Practices