Who should manage the product scope?

The correct answer is D. Project manager. The Project Manager is responsible for managing product scope - ensuring that the project delivers exactly what was agreed upon, no more and no less. While a Business Analyst helps elicit and document requirements, and the Project Sponsor approves scope at a high level, it is…

Project Management Fundamentals and Core Concepts

Question

Who should manage the product scope?

Options

  • ABusiness analyst
  • BScope manager
  • CProject sponsor
  • DProject manager

How the community answered

(27 responses)
  • B
    4% (1)
  • C
    4% (1)
  • D
    93% (25)

Explanation

The Project Manager is responsible for managing product scope - ensuring that the project delivers exactly what was agreed upon, no more and no less. While a Business Analyst helps elicit and document requirements, and the Project Sponsor approves scope at a high level, it is the Project Manager who controls scope changes, manages the scope baseline, and prevents scope creep. 'Scope Manager' is not a standard project role.