PMIPMI
CAPM · Question #513
CAPM Question #513: Real Exam Question with Answer & Explanation
The correct answer is B: Total float. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
Which of the following is provided by the critical path method?
Options
- ASchedule float
- BTotal float
- CSchedule value
- DEarned value (EV)
Topics
#Critical Path Method#Total Float#Schedule Management#Project Scheduling
Community Discussion
No community discussion yet for this question.