CAPM · Question #444
What estimating technique is used when there is limited information?
The correct answer is A. Analogous estimating. Analogous estimating (also called top-down estimating) relies on historical data from similar past projects to estimate the current project's cost, duration, or scope. It is specifically designed for use early in a project or when detailed information is unavailable, making it id
Question
Options
- AAnalogous estimating
- BParametric estimating
- CBottom-up estimating
- DThree-point estimating
How the community answered
(29 responses)- A93% (27)
- B3% (1)
- C3% (1)
Explanation
Analogous estimating (also called top-down estimating) relies on historical data from similar past projects to estimate the current project's cost, duration, or scope. It is specifically designed for use early in a project or when detailed information is unavailable, making it ideal for situations with limited information. It is faster and less costly to produce than other techniques but is also less accurate. Parametric estimating (B) requires a statistical relationship between variables and historical data-it needs more structured data. Bottom-up estimating (C) requires detailed decomposition of every work package, which is impossible without sufficient information. Three-point estimating (D) requires optimistic, pessimistic, and most-likely estimates for each activity-more detail than analogous requires.
Topics
Community Discussion
No community discussion yet for this question.