CAPM · Question #438
What risk response strategy involves removing high-risk scope elements from a project?
The correct answer is B. Avoid. Avoid is a negative risk (threat) response strategy that eliminates the threat entirely by removing its cause. Removing a high-risk scope element-such as cutting a technically risky feature-is a classic example of avoidance because it eliminates the possibility of the risk…
Question
Options
- ATransfer
- BAvoid
- CExploit
- DAccept
How the community answered
(36 responses)- A6% (2)
- B92% (33)
- D3% (1)
Explanation
Avoid is a negative risk (threat) response strategy that eliminates the threat entirely by removing its cause. Removing a high-risk scope element-such as cutting a technically risky feature-is a classic example of avoidance because it eliminates the possibility of the risk occurring. Transfer (A) shifts the financial impact to a third party (e.g., insurance, contracting) but does not remove the scope. Exploit (C) is a positive risk (opportunity) strategy, not applicable to threats. Accept (D) means acknowledging the risk and either setting aside contingency reserves or doing nothing, but the risk and the scope remain.
Topics