nerdexam
PMI

CAPM · Question #39

Which are the competing constraints that a project manager should address when tailoring a project?

The correct answer is A. Cost, scope, schedule. This question tests knowledge of the primary competing constraints a project manager must balance when tailoring a project.

Predictive, Plan-Based Methodologies

Question

Which are the competing constraints that a project manager should address when tailoring a project?

Options

  • ACost, scope, schedule
  • BSponsorship, risk, quality
  • CSchedule, sponsorship, scope
  • DResources, quality, communication

How the community answered

(48 responses)
  • A
    92% (44)
  • B
    2% (1)
  • C
    4% (2)
  • D
    2% (1)

Why each option

This question tests knowledge of the primary competing constraints a project manager must balance when tailoring a project.

ACost, scope, scheduleCorrect

Cost, scope, and schedule form the foundational triple constraint in project management, and the PMBOK Guide identifies these - along with quality, resources, and risk - as the competing constraints that a project manager must address when tailoring a project. Among the answer choices, only option A correctly names the three core elements of the triple constraint that every project manager must balance.

BSponsorship, risk, quality

Sponsorship is not a competing constraint - it is a governance and support factor; while risk and quality are constraints, sponsorship does not belong in this grouping.

CSchedule, sponsorship, scope

Sponsorship is not a recognized project constraint; replacing cost with sponsorship makes this option incorrect.

DResources, quality, communication

Resources, quality, and communication are important project factors, but communication is not listed as a core competing constraint in the PMBOK's constraint model.

Concept tested: Triple constraint and competing project constraints

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Project Constraints#Triple Constraint#Project Tailoring#Scope Management

Community Discussion

No community discussion yet for this question.

Full CAPM Practice