CAPM · Question #39
Which are the competing constraints that a project manager should address when tailoring a project?
The correct answer is A. Cost, scope, schedule. This question tests knowledge of the primary competing constraints a project manager must balance when tailoring a project.
Question
Options
- ACost, scope, schedule
- BSponsorship, risk, quality
- CSchedule, sponsorship, scope
- DResources, quality, communication
How the community answered
(48 responses)- A92% (44)
- B2% (1)
- C4% (2)
- D2% (1)
Why each option
This question tests knowledge of the primary competing constraints a project manager must balance when tailoring a project.
Cost, scope, and schedule form the foundational triple constraint in project management, and the PMBOK Guide identifies these - along with quality, resources, and risk - as the competing constraints that a project manager must address when tailoring a project. Among the answer choices, only option A correctly names the three core elements of the triple constraint that every project manager must balance.
Sponsorship is not a competing constraint - it is a governance and support factor; while risk and quality are constraints, sponsorship does not belong in this grouping.
Sponsorship is not a recognized project constraint; replacing cost with sponsorship makes this option incorrect.
Resources, quality, and communication are important project factors, but communication is not listed as a core competing constraint in the PMBOK's constraint model.
Concept tested: Triple constraint and competing project constraints
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok
Topics
Community Discussion
No community discussion yet for this question.