PMIPMI
CAPM · Question #388
CAPM Question #388: Real Exam Question with Answer & Explanation
The correct answer is C: Estimate Costs. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
The project manager and project team are developing approximations of the cost of resources needed to complete the project work. On which process are they working?
Options
- APlan Cost Management
- BEstimate Activity Resources
- CEstimate Costs
- DDetermine Budget
Topics
#Project Cost Management#Estimate Costs process#Cost estimation#Project planning
Community Discussion
No community discussion yet for this question.