CAPM · Question #388
The project manager and project team are developing approximations of the cost of resources needed to complete the project work. On which process are they working?
The correct answer is C. Estimate Costs. Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project work. Plan Cost Management (A) establishes how costs will be managed, not estimated. Estimate Activity Resources (B) identifies the types and quantities of resources
Question
Options
- APlan Cost Management
- BEstimate Activity Resources
- CEstimate Costs
- DDetermine Budget
How the community answered
(27 responses)- A4% (1)
- B4% (1)
- C93% (25)
Explanation
Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project work. Plan Cost Management (A) establishes how costs will be managed, not estimated. Estimate Activity Resources (B) identifies the types and quantities of resources needed, not their costs. Determine Budget (D) aggregates estimated costs into a cost baseline. The key phrase 'approximations of the cost of resources' is the textbook definition of Estimate Costs.
Topics
Community Discussion
No community discussion yet for this question.