nerdexam
PMIPMI

CAPM · Question #388

CAPM Question #388: Real Exam Question with Answer & Explanation

The correct answer is C: Estimate Costs. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

The project manager and project team are developing approximations of the cost of resources needed to complete the project work. On which process are they working?

Options

  • APlan Cost Management
  • BEstimate Activity Resources
  • CEstimate Costs
  • DDetermine Budget

Topics

#Project Cost Management#Estimate Costs process#Cost estimation#Project planning

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions