CAPM · Question #366
Which tools and techniques should a project manager use when estimating costs?
The correct answer is C. Three-point estimating and risk register. Three-point estimating is a recognized cost estimation technique in the PMBOK that uses three values - optimistic (O), pessimistic (P), and most likely (M) - to produce a more accurate estimate by accounting for uncertainty. The risk register is consulted during cost estimation…
Question
Options
- ALessons learned register and cost aggregation
- BProject schedule and resources requirements
- CThree-point estimating and risk register
- DExpert judgment and decision making
How the community answered
(36 responses)- A3% (1)
- B3% (1)
- C89% (32)
- D6% (2)
Explanation
Three-point estimating is a recognized cost estimation technique in the PMBOK that uses three values - optimistic (O), pessimistic (P), and most likely (M) - to produce a more accurate estimate by accounting for uncertainty. The risk register is consulted during cost estimation to identify risk-related costs and factor in contingency reserves. Together, they form a valid pairing of tool and input used in the Estimate Costs process. Option A is incorrect because 'lessons learned register' is an input, not a technique, and 'cost aggregation' is used in Determine Budget, not estimation. Option B lists inputs (schedule, resource requirements), not tools or techniques. Option D, while 'expert judgment' is a valid technique, 'decision making' is too generic and not a defined cost estimation tool.
Topics
Community Discussion
No community discussion yet for this question.