nerdexam
PMIPMI

CAPM · Question #366

CAPM Question #366: Real Exam Question with Answer & Explanation

The correct answer is C: Three-point estimating and risk register. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

Which tools and techniques should a project manager use when estimating costs?

Options

  • ALessons learned register and cost aggregation
  • BProject schedule and resources requirements
  • CThree-point estimating and risk register
  • DExpert judgment and decision making

Topics

#Cost Estimation#Three-point Estimating#Project Cost Management#Risk Consideration

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions