nerdexam
PMI

CAPM · Question #366

Which tools and techniques should a project manager use when estimating costs?

The correct answer is C. Three-point estimating and risk register. Three-point estimating is a recognized cost estimation technique in the PMBOK that uses three values - optimistic (O), pessimistic (P), and most likely (M) - to produce a more accurate estimate by accounting for uncertainty. The risk register is consulted during cost estimation…

Predictive, Plan-Based Methodologies

Question

Which tools and techniques should a project manager use when estimating costs?

Options

  • ALessons learned register and cost aggregation
  • BProject schedule and resources requirements
  • CThree-point estimating and risk register
  • DExpert judgment and decision making

How the community answered

(36 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    89% (32)
  • D
    6% (2)

Explanation

Three-point estimating is a recognized cost estimation technique in the PMBOK that uses three values - optimistic (O), pessimistic (P), and most likely (M) - to produce a more accurate estimate by accounting for uncertainty. The risk register is consulted during cost estimation to identify risk-related costs and factor in contingency reserves. Together, they form a valid pairing of tool and input used in the Estimate Costs process. Option A is incorrect because 'lessons learned register' is an input, not a technique, and 'cost aggregation' is used in Determine Budget, not estimation. Option B lists inputs (schedule, resource requirements), not tools or techniques. Option D, while 'expert judgment' is a valid technique, 'decision making' is too generic and not a defined cost estimation tool.

Topics

#Cost Estimation#Three-point Estimating#Project Cost Management#Risk Consideration

Community Discussion

No community discussion yet for this question.

Full CAPM Practice