PMIPMI
CAPM · Question #360
CAPM Question #360: Real Exam Question with Answer & Explanation
The correct answer is C: Milestone list and Risk Register. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
When developing a schedule which tools and techniques should a project manager use?
Options
- ASchedule Network Analysis and Critical Path Method
- BActivity list and Expert Judgement
- CMilestone list and Risk Register
- DBasis on estimates and Rolling Wave Planning
Topics
#Schedule Development#Project Planning#Milestone Management#Risk Management Integration
Community Discussion
No community discussion yet for this question.