CAPM · Question #360

CAPM Question #360: Real Exam Question with Answer & Explanation

The correct answer is C: Milestone list and Risk Register. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

When developing a schedule which tools and techniques should a project manager use?

Options

  • ASchedule Network Analysis and Critical Path Method
  • BActivity list and Expert Judgement
  • CMilestone list and Risk Register
  • DBasis on estimates and Rolling Wave Planning

Topics

#Schedule Development#Project Planning#Milestone Management#Risk Management Integration