nerdexam
PMIPMI

CAPM · Question #350

CAPM Question #350: Real Exam Question with Answer & Explanation

The correct answer is D: Project management plan. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

Which of the following is used as input to prepare a cost management plan?

Options

  • AExpert judgment
  • BLessons learned
  • CCost estimation
  • DProject management plan

Topics

#Cost Management#Project Planning#PMBOK Processes#Inputs

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions