nerdexam
PMIPMI

CAPM · Question #340

CAPM Question #340: Real Exam Question with Answer & Explanation

The correct answer is C: Deliverable acceptance. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

A project is at the closing stage. The project manager asks the team to perform closing functions at the next meeting. Which two procedures will the project team perform? (Choose two.)

Options

  • AStakeholder mapping
  • BIssue log update
  • CDeliverable acceptance
  • DProject audit
  • ERisk register tracking

Topics

#Project Closure#Closing Process Group#Deliverable Acceptance#Project Audit

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions