nerdexam
PMIPMI

CAPM · Question #301

CAPM Question #301: Real Exam Question with Answer & Explanation

The correct answer is D: Analogous. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

Based on a previous project that has been completed, a project manager decides the best way to estimate costs is through historical data. What kind of estimating is this?

Options

  • ABottom-up
  • BThree-point
  • CParametric
  • DAnalogous

Topics

#Cost Estimating#Analogous Estimating#Estimating Techniques#Project Cost Management

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions