nerdexam
PMI

CAPM · Question #301

Based on a previous project that has been completed, a project manager decides the best way to estimate costs is through historical data. What kind of estimating is this?

The correct answer is D. Analogous. Analogous estimating (also called top-down estimating) uses actual costs, durations, or other parameters from a previous, similar project as the basis for estimating the current project. It is faster and less expensive than detailed estimating methods but is generally less…

Predictive, Plan-Based Methodologies

Question

Based on a previous project that has been completed, a project manager decides the best way to estimate costs is through historical data. What kind of estimating is this?

Options

  • ABottom-up
  • BThree-point
  • CParametric
  • DAnalogous

How the community answered

(24 responses)
  • A
    4% (1)
  • C
    4% (1)
  • D
    92% (22)

Explanation

Analogous estimating (also called top-down estimating) uses actual costs, durations, or other parameters from a previous, similar project as the basis for estimating the current project. It is faster and less expensive than detailed estimating methods but is generally less accurate. Bottom-up estimating builds estimates from individual work package details. Parametric estimating uses statistical relationships between historical data and project variables (e.g., cost per unit). Three-point estimating calculates a weighted average using optimistic, most likely, and pessimistic values. Using a completed project's historical data as the foundation is the hallmark of analogous estimating.

Topics

#Cost Estimating#Analogous Estimating#Estimating Techniques#Project Cost Management

Community Discussion

No community discussion yet for this question.

Full CAPM Practice