CAPM · Question #301
Based on a previous project that has been completed, a project manager decides the best way to estimate costs is through historical data. What kind of estimating is this?
The correct answer is D. Analogous. Analogous estimating (also called top-down estimating) uses actual costs, durations, or other parameters from a previous, similar project as the basis for estimating the current project. It is faster and less expensive than detailed estimating methods but is generally less…
Question
Options
- ABottom-up
- BThree-point
- CParametric
- DAnalogous
How the community answered
(24 responses)- A4% (1)
- C4% (1)
- D92% (22)
Explanation
Analogous estimating (also called top-down estimating) uses actual costs, durations, or other parameters from a previous, similar project as the basis for estimating the current project. It is faster and less expensive than detailed estimating methods but is generally less accurate. Bottom-up estimating builds estimates from individual work package details. Parametric estimating uses statistical relationships between historical data and project variables (e.g., cost per unit). Three-point estimating calculates a weighted average using optimistic, most likely, and pessimistic values. Using a completed project's historical data as the foundation is the hallmark of analogous estimating.
Topics
Community Discussion
No community discussion yet for this question.