CAPM · Question #282
Which key benefit can a project manager obtain by identifying stakeholders?
The correct answer is A. Identify the appropriate focus for engagement of each stakeholder. Per PMBOK, the key benefit of the Identify Stakeholders process is that it enables the project manager to identify the appropriate focus for engagement of each stakeholder (A). Understanding who stakeholders are, their interests, influence, and involvement allows the PM to tailor
Question
Options
- AIdentify the appropriate focus for engagement of each stakeholder
- BAssess the risk exposure for each stakeholder
- CMap stakeholder power and influence grid
- DIdentify the appropriate channels of communication with all stakeholders
How the community answered
(21 responses)- A95% (20)
- D5% (1)
Explanation
Per PMBOK, the key benefit of the Identify Stakeholders process is that it enables the project manager to identify the appropriate focus for engagement of each stakeholder (A). Understanding who stakeholders are, their interests, influence, and involvement allows the PM to tailor engagement strategies appropriately. Assessing risk exposure per stakeholder (B) is part of risk management analysis, not a stated benefit of stakeholder identification. Mapping power/influence grids (C) is a tool used within the identification process, not the benefit itself. Identifying communication channels (D) is a benefit of Plan Communications Management, which occurs after stakeholders are identified. The Identify Stakeholders process is specifically about determining who is affected and how best to engage them.