CAPM · Question #282

Which key benefit can a project manager obtain by identifying stakeholders?

The correct answer is A. Identify the appropriate focus for engagement of each stakeholder. Per PMBOK, the key benefit of the Identify Stakeholders process is that it enables the project manager to identify the appropriate focus for engagement of each stakeholder (A). Understanding who stakeholders are, their interests, influence, and involvement allows the PM to tailor

Predictive, Plan-Based Methodologies

Question

Which key benefit can a project manager obtain by identifying stakeholders?

Options

  • AIdentify the appropriate focus for engagement of each stakeholder
  • BAssess the risk exposure for each stakeholder
  • CMap stakeholder power and influence grid
  • DIdentify the appropriate channels of communication with all stakeholders

How the community answered

(21 responses)
  • A
    95% (20)
  • D
    5% (1)

Explanation

Per PMBOK, the key benefit of the Identify Stakeholders process is that it enables the project manager to identify the appropriate focus for engagement of each stakeholder (A). Understanding who stakeholders are, their interests, influence, and involvement allows the PM to tailor engagement strategies appropriately. Assessing risk exposure per stakeholder (B) is part of risk management analysis, not a stated benefit of stakeholder identification. Mapping power/influence grids (C) is a tool used within the identification process, not the benefit itself. Identifying communication channels (D) is a benefit of Plan Communications Management, which occurs after stakeholders are identified. The Identify Stakeholders process is specifically about determining who is affected and how best to engage them.

Topics

#Stakeholder Identification#Stakeholder Engagement#Project Management Processes#PMBOK Guide

Community Discussion