CAPM · Question #280

The project manager is dividing the project scope into smaller pieces, and repeating this process until no more subdivisions are required. At this point the project manager is able to estimate costs a

The correct answer is B. Work packages. The elements reached at the lowest level of WBS decomposition-where no further subdivision is needed and costs and activities can be estimated-are called work packages (B). Work packages are the fundamental building blocks of the Work Breakdown Structure (WBS) and represent deliv

Predictive, Plan-Based Methodologies

Question

The project manager is dividing the project scope into smaller pieces, and repeating this process until no more subdivisions are required. At this point the project manager is able to estimate costs and activities for each element. What are these elements called?

Options

  • AProject activities
  • BWork packages
  • CPlanning packages
  • DProject deliverables

How the community answered

(43 responses)
  • A
    2% (1)
  • B
    91% (39)
  • C
    2% (1)
  • D
    5% (2)

Explanation

The elements reached at the lowest level of WBS decomposition-where no further subdivision is needed and costs and activities can be estimated-are called work packages (B). Work packages are the fundamental building blocks of the Work Breakdown Structure (WBS) and represent deliverable-oriented components that can be scheduled, cost-estimated, monitored, and controlled. Project activities (A) are derived from work packages through the Define Activities process-they are one level below work packages. Planning packages (C) are WBS components below control accounts but above work packages, used when detailed planning is not yet possible. Project deliverables (D) are higher-level outcomes that are decomposed into work packages, not the result of decomposition.

Topics

#Work Breakdown Structure#Work packages#Scope management#Decomposition