nerdexam
PMIPMI

CAPM · Question #280

CAPM Question #280: Real Exam Question with Answer & Explanation

The correct answer is B: Work packages. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

The project manager is dividing the project scope into smaller pieces, and repeating this process until no more subdivisions are required. At this point the project manager is able to estimate costs and activities for each element. What are these elements called?

Options

  • AProject activities
  • BWork packages
  • CPlanning packages
  • DProject deliverables

Topics

#Work Breakdown Structure#Work packages#Scope management#Decomposition

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions