PMIPMI
CAPM · Question #280
CAPM Question #280: Real Exam Question with Answer & Explanation
The correct answer is B: Work packages. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
The project manager is dividing the project scope into smaller pieces, and repeating this process until no more subdivisions are required. At this point the project manager is able to estimate costs and activities for each element. What are these elements called?
Options
- AProject activities
- BWork packages
- CPlanning packages
- DProject deliverables
Topics
#Work Breakdown Structure#Work packages#Scope management#Decomposition
Community Discussion
No community discussion yet for this question.