CAPM · Question #275
What specific quality considerations should be examined while completing Quality Management plan?
The correct answer is D. Standards and regulatory compliance. When developing a Quality Management Plan, the project manager must examine standards and regulatory compliance (D) as a core quality consideration. The plan must define how the project will adhere to relevant industry standards, legal requirements, and regulatory frameworks that
Question
Options
- ARisk register
- BStakeholder engagement
- CContinuous improvement
- DStandards and regulatory compliance
How the community answered
(42 responses)- A2% (1)
- B2% (1)
- C5% (2)
- D90% (38)
Explanation
When developing a Quality Management Plan, the project manager must examine standards and regulatory compliance (D) as a core quality consideration. The plan must define how the project will adhere to relevant industry standards, legal requirements, and regulatory frameworks that govern the deliverables. Risk register (A) is an input to quality planning but is not itself a quality consideration; stakeholder engagement (B) belongs to communications and stakeholder management; and continuous improvement (C) is a quality principle/philosophy, not a specific consideration examined during the planning phase. PMBOK emphasizes that quality standards and compliance requirements directly shape quality metrics, audits, and acceptance criteria.
Topics
Community Discussion
No community discussion yet for this question.