CAPM · Question #275

What specific quality considerations should be examined while completing Quality Management plan?

The correct answer is D. Standards and regulatory compliance. When developing a Quality Management Plan, the project manager must examine standards and regulatory compliance (D) as a core quality consideration. The plan must define how the project will adhere to relevant industry standards, legal requirements, and regulatory frameworks that

Predictive, Plan-Based Methodologies

Question

What specific quality considerations should be examined while completing Quality Management plan?

Options

  • ARisk register
  • BStakeholder engagement
  • CContinuous improvement
  • DStandards and regulatory compliance

How the community answered

(42 responses)
  • A
    2% (1)
  • B
    2% (1)
  • C
    5% (2)
  • D
    90% (38)

Explanation

When developing a Quality Management Plan, the project manager must examine standards and regulatory compliance (D) as a core quality consideration. The plan must define how the project will adhere to relevant industry standards, legal requirements, and regulatory frameworks that govern the deliverables. Risk register (A) is an input to quality planning but is not itself a quality consideration; stakeholder engagement (B) belongs to communications and stakeholder management; and continuous improvement (C) is a quality principle/philosophy, not a specific consideration examined during the planning phase. PMBOK emphasizes that quality standards and compliance requirements directly shape quality metrics, audits, and acceptance criteria.

Topics

#Quality Management#Quality Management Plan#Standards and Compliance#Planning Process