CAPM · Question #257
What key component of the project charter defines the conditions for closing a project phase?
The correct answer is C. Exit criteria. Exit criteria are the specific conditions that must be satisfied before a project phase can be formally closed and the project can proceed to the next phase (or be fully closed). They serve as the measurable gates that govern phase transitions. 'Purpose' (A) explains why the…
Question
Options
- APurpose
- BApproval requires
- CExit criteria
- DHigh-level requirements
How the community answered
(65 responses)- A3% (2)
- B2% (1)
- C91% (59)
- D5% (3)
Explanation
Exit criteria are the specific conditions that must be satisfied before a project phase can be formally closed and the project can proceed to the next phase (or be fully closed). They serve as the measurable gates that govern phase transitions. 'Purpose' (A) explains why the project exists. 'Approval requirements' (B) identify who must sign off on deliverables or decisions. 'High-level requirements' (D) describe what the project must produce. Only exit criteria explicitly define the conditions under which a phase ends - making them the component that controls phase closure.
Topics
Community Discussion
No community discussion yet for this question.