nerdexam
PMI

CAPM · Question #237

Given the following information: Activity A takes one week. Activity B takes three weeks. Activity C takes two weeks. Activity D takes five weeks. Activity A starts at the same time as Activity B. Act

The correct answer is C. 10 weeks. Activities A (1 week) and B (3 weeks) run in parallel. Activity C cannot start until BOTH A and B are complete, so C starts at the end of week 3 (the later of the two) and finishes at the end of week 5 (3 + 2). Activity D starts at week 5 and takes 5 weeks, finishing at week 10.

Predictive, Plan-Based Methodologies

Question

Given the following information:
  • Activity A takes one week.
  • Activity B takes three weeks.
  • Activity C takes two weeks.
  • Activity D takes five weeks.
  • Activity A starts at the same time as Activity B.
  • Activity C follows Activity B and Activity A.
  • Activity D follows Activity C. How long will it take to complete the project?

Options

  • A8 weeks
  • B9 weeks
  • C10 weeks
  • D11 weeks

How the community answered

(20 responses)
  • A
    5% (1)
  • B
    5% (1)
  • C
    80% (16)
  • D
    10% (2)

Explanation

Activities A (1 week) and B (3 weeks) run in parallel. Activity C cannot start until BOTH A and B are complete, so C starts at the end of week 3 (the later of the two) and finishes at the end of week 5 (3 + 2). Activity D starts at week 5 and takes 5 weeks, finishing at week 10. The critical path is B → C → D = 3 + 2 + 5 = 10 weeks. Activity A (1 week) is not on the critical path since it finishes before B.

Topics

#Activity sequencing#Project duration calculation#Critical path method#Schedule network analysis

Community Discussion

No community discussion yet for this question.

Full CAPM Practice