PMIPMI
CAPM · Question #237
CAPM Question #237: Real Exam Question with Answer & Explanation
The correct answer is C: 10 weeks. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
Given the following information: - Activity A takes one week. - Activity B takes three weeks. - Activity C takes two weeks. - Activity D takes five weeks. - Activity A starts at the same time as Activity B. - Activity C follows Activity B and Activity A. - Activity D follows Activity C. How long will it take to complete the project?
Options
- A8 weeks
- B9 weeks
- C10 weeks
- D11 weeks
Topics
#Activity sequencing#Project duration calculation#Critical path method#Schedule network analysis
Community Discussion
No community discussion yet for this question.