CAPM · Question #237
Given the following information: Activity A takes one week. Activity B takes three weeks. Activity C takes two weeks. Activity D takes five weeks. Activity A starts at the same time as Activity B. Act
The correct answer is C. 10 weeks. Activities A (1 week) and B (3 weeks) run in parallel. Activity C cannot start until BOTH A and B are complete, so C starts at the end of week 3 (the later of the two) and finishes at the end of week 5 (3 + 2). Activity D starts at week 5 and takes 5 weeks, finishing at week 10.
Question
- Activity A takes one week.
- Activity B takes three weeks.
- Activity C takes two weeks.
- Activity D takes five weeks.
- Activity A starts at the same time as Activity B.
- Activity C follows Activity B and Activity A.
- Activity D follows Activity C. How long will it take to complete the project?
Options
- A8 weeks
- B9 weeks
- C10 weeks
- D11 weeks
How the community answered
(20 responses)- A5% (1)
- B5% (1)
- C80% (16)
- D10% (2)
Explanation
Activities A (1 week) and B (3 weeks) run in parallel. Activity C cannot start until BOTH A and B are complete, so C starts at the end of week 3 (the later of the two) and finishes at the end of week 5 (3 + 2). Activity D starts at week 5 and takes 5 weeks, finishing at week 10. The critical path is B → C → D = 3 + 2 + 5 = 10 weeks. Activity A (1 week) is not on the critical path since it finishes before B.
Topics
Community Discussion
No community discussion yet for this question.