nerdexam
PMIPMI

CAPM · Question #237

CAPM Question #237: Real Exam Question with Answer & Explanation

The correct answer is C: 10 weeks. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

Given the following information: - Activity A takes one week. - Activity B takes three weeks. - Activity C takes two weeks. - Activity D takes five weeks. - Activity A starts at the same time as Activity B. - Activity C follows Activity B and Activity A. - Activity D follows Activity C. How long will it take to complete the project?

Options

  • A8 weeks
  • B9 weeks
  • C10 weeks
  • D11 weeks

Topics

#Activity sequencing#Project duration calculation#Critical path method#Schedule network analysis

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions