CAPM · Question #235

Which of the following tasks focuses on decomposing work packages?

The correct answer is B. Define activities. Define Activities is the process of breaking down work packages from the WBS into smaller, more manageable schedule activities. This decomposition is key to creating a realistic schedule. Adjusting duration estimates (A) modifies existing time estimates rather than decomposing wo

Predictive, Plan-Based Methodologies

Question

Which of the following tasks focuses on decomposing work packages?

Options

  • AAdjust duration estimates
  • BDefine activities
  • CComplete rolling wave planning
  • DDevelop milestone list

How the community answered

(57 responses)
  • A
    7% (4)
  • B
    88% (50)
  • C
    2% (1)
  • D
    4% (2)

Explanation

Define Activities is the process of breaking down work packages from the WBS into smaller, more manageable schedule activities. This decomposition is key to creating a realistic schedule. Adjusting duration estimates (A) modifies existing time estimates rather than decomposing work. Rolling wave planning (C) is an iterative planning technique, not a decomposition task. Developing the milestone list (D) identifies significant project events but does not decompose work packages.

Topics

#Define Activities#Work Breakdown Structure#Scope Management#Decomposition