Which of the following tasks focuses on decomposing work packages?
The correct answer is B. Define activities. Define Activities is the process of breaking down work packages from the WBS into smaller, more manageable schedule activities. This decomposition is key to creating a realistic schedule. Adjusting duration estimates (A) modifies existing time estimates rather than decomposing wo
Question
Options
- AAdjust duration estimates
- BDefine activities
- CComplete rolling wave planning
- DDevelop milestone list
How the community answered
(57 responses)- A7% (4)
- B88% (50)
- C2% (1)
- D4% (2)
Explanation
Define Activities is the process of breaking down work packages from the WBS into smaller, more manageable schedule activities. This decomposition is key to creating a realistic schedule. Adjusting duration estimates (A) modifies existing time estimates rather than decomposing work. Rolling wave planning (C) is an iterative planning technique, not a decomposition task. Developing the milestone list (D) identifies significant project events but does not decompose work packages.
Topics
Community Discussion
No community discussion yet for this question.