Which project documents can determine the budget?
Options
- AProcurement documents, contracts, requirements documentation, and basis of estimates
- BBasis of estimates, cost estimates, project schedule, and risk register
- CBusiness case, project charter, statement of work, and cost estimates
- DScope baseline, resource management plan, activity list, and assumption log
Topics
#Cost Management#Budgeting#Project Documents#Determine Budget Process