PMIPMI
CAPM · Question #21
CAPM Question #21: Real Exam Question with Answer & Explanation
The correct answer is A: Stakeholder engagement plan and organizational process assets. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
A project manager is working on the communications management plan. Which of these documents are inputs to consider?
Options
- AStakeholder engagement plan and organizational process assets
- BProject schedule and stakeholder register
- CQuality management plan and risk register
- DBasis of estimates and scope baseline
Topics
#Communications Management#Planning Process Group#Stakeholder Management#ITTOs
Community Discussion
No community discussion yet for this question.