nerdexam
PMI

CAPM · Question #164

Which components of the project management plan are inputs used when creating the stakeholder engagement plan?

The correct answer is A. Risk, resource, and communications management plans. When developing the Stakeholder Engagement Plan, the PMBOK Guide specifies that the relevant project management plan components used as inputs are the resource management plan, communications management plan, and risk management plan. The resource management plan covers team role

Predictive, Plan-Based Methodologies

Question

Which components of the project management plan are inputs used when creating the stakeholder engagement plan?

Options

  • ARisk, resource, and communications management plans
  • BScope, quality, and resource management plans
  • CProcurement, integration, and risk management plans
  • DCommunications, schedule, and cost management plans

How the community answered

(30 responses)
  • A
    87% (26)
  • B
    3% (1)
  • C
    3% (1)
  • D
    7% (2)

Explanation

When developing the Stakeholder Engagement Plan, the PMBOK Guide specifies that the relevant project management plan components used as inputs are the resource management plan, communications management plan, and risk management plan. The resource management plan covers team roles affecting stakeholder interaction; the communications management plan defines how stakeholders will receive information; and the risk management plan addresses risk tolerances relevant to stakeholder engagement. The other answer choices include components (scope, quality, procurement, schedule, cost) that are not primary inputs to this specific planning process.

Topics

#Stakeholder Engagement#Project Management Plan Inputs#Planning Process Group#Communications Management

Community Discussion

No community discussion yet for this question.

Full CAPM Practice