PMIPMI
CAPM · Question #164
CAPM Question #164: Real Exam Question with Answer & Explanation
The correct answer is A: Risk, resource, and communications management plans. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
Which components of the project management plan are inputs used when creating the stakeholder engagement plan?
Options
- ARisk, resource, and communications management plans
- BScope, quality, and resource management plans
- CProcurement, integration, and risk management plans
- DCommunications, schedule, and cost management plans
Topics
#Stakeholder Engagement#Project Management Plan Inputs#Planning Process Group#Communications Management
Community Discussion
No community discussion yet for this question.