nerdexam
PMIPMI

CAPM · Question #164

CAPM Question #164: Real Exam Question with Answer & Explanation

The correct answer is A: Risk, resource, and communications management plans. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

Which components of the project management plan are inputs used when creating the stakeholder engagement plan?

Options

  • ARisk, resource, and communications management plans
  • BScope, quality, and resource management plans
  • CProcurement, integration, and risk management plans
  • DCommunications, schedule, and cost management plans

Topics

#Stakeholder Engagement#Project Management Plan Inputs#Planning Process Group#Communications Management

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions