The correct answer is D: Conduct a quality audit. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

How can a project manager determine if the project activities comply with organizational and project policies, processes, and procedures?

Options

  • ALook at the quality metrics
  • BValidate the scope
  • CReview the quality checklist
  • DConduct a quality audit

Topics

#Quality Audit#Process Compliance#Quality Management