nerdexam
PMIPMI

CAPM · Question #151

CAPM Question #151: Real Exam Question with Answer & Explanation

The correct answer is A: List of identified risks, potential risk owners, list of potential risk response. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

Which of the following must be included in the risk register when the project manager completes the Identify Risks process?

Options

  • AList of identified risks, potential risk owners, list of potential risk response
  • BList of identified risks, list of causes, list of risk categories
  • CShort risk titles, list of potential risk owners, list of impacts on objectives
  • DList of activities affected, list of potential risk responses, list of causes

Topics

#Risk Management#Identify Risks Process#Risk Register#Project Documents

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions