PMIPMI
CAPM · Question #151
CAPM Question #151: Real Exam Question with Answer & Explanation
The correct answer is A: List of identified risks, potential risk owners, list of potential risk response. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
Which of the following must be included in the risk register when the project manager completes the Identify Risks process?
Options
- AList of identified risks, potential risk owners, list of potential risk response
- BList of identified risks, list of causes, list of risk categories
- CShort risk titles, list of potential risk owners, list of impacts on objectives
- DList of activities affected, list of potential risk responses, list of causes
Topics
#Risk Management#Identify Risks Process#Risk Register#Project Documents
Community Discussion
No community discussion yet for this question.