CAPM · Question #151
Which of the following must be included in the risk register when the project manager completes the Identify Risks process?
The correct answer is A. List of identified risks, potential risk owners, list of potential risk response. According to the PMBOK Guide, the risk register is the primary output of the Identify Risks process. At this stage, it must contain: (1) a list of identified risks with descriptions, (2) a list of potential risk owners (individuals or groups best positioned to respond to each…
Question
Options
- AList of identified risks, potential risk owners, list of potential risk response
- BList of identified risks, list of causes, list of risk categories
- CShort risk titles, list of potential risk owners, list of impacts on objectives
- DList of activities affected, list of potential risk responses, list of causes
How the community answered
(27 responses)- A93% (25)
- B4% (1)
- C4% (1)
Explanation
According to the PMBOK Guide, the risk register is the primary output of the Identify Risks process. At this stage, it must contain: (1) a list of identified risks with descriptions, (2) a list of potential risk owners (individuals or groups best positioned to respond to each risk), and (3) a list of potential risk responses (preliminary responses that may be refined later in the Plan Risk Responses process). Option B is incorrect because 'list of risk categories' is an input (from the risk breakdown structure), not an output. Option C is incorrect because 'list of impacts on objectives' is not a standard risk register component at this stage. Option D is incorrect because 'list of activities affected' is not a required risk register element.