nerdexam
PMIPMI

CAPM · Question #134

CAPM Question #134: Real Exam Question with Answer & Explanation

The correct answer is A: Estimate Costs and Determine Budget. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

Which two processes should be used to influence costs in the early stages of a project?

Options

  • AEstimate Costs and Determine Budget
  • BPlan Cost Management and Estimate Activity Durations
  • CControl Quality and Control Costs
  • DPlan Stakeholder Engagement and Plan Communications Management

Topics

#Cost Management#Project Planning#Estimate Costs#Determine Budget

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions