nerdexam
PMI

CAPM · Question #126

Perform Quantitative Risk Analysis focuses on:

The correct answer is D. analyzing numerically the impact of individual risks on the overall project's time and cost objectives. Perform Quantitative Risk Analysis numerically models the combined effect of identified risks on overall project objectives, particularly time and cost.

Predictive, Plan-Based Methodologies

Question

Perform Quantitative Risk Analysis focuses on:

Options

  • Acompiling a list of known risks and preparing responses to them
  • Bassessing the probability of occurrence and impact for every risk in the project
  • Cevaluating the contingency and management reserves required for the project
  • Danalyzing numerically the impact of individual risks on the overall project's time and cost objectives

How the community answered

(48 responses)
  • A
    4% (2)
  • B
    2% (1)
  • C
    4% (2)
  • D
    90% (43)

Why each option

Perform Quantitative Risk Analysis numerically models the combined effect of identified risks on overall project objectives, particularly time and cost.

Acompiling a list of known risks and preparing responses to them

Compiling a list of known risks and preparing responses describes the Identify Risks and Plan Risk Responses processes, not Quantitative Risk Analysis.

Bassessing the probability of occurrence and impact for every risk in the project

Assessing probability of occurrence and impact for each risk describes Perform Qualitative Risk Analysis, which uses subjective scales rather than numerical modeling.

Cevaluating the contingency and management reserves required for the project

Evaluating contingency and management reserves is an output informed by Quantitative Risk Analysis but is not the definition of the process itself.

Danalyzing numerically the impact of individual risks on the overall project's time and cost objectivesCorrect

Quantitative Risk Analysis uses numerical techniques such as Monte Carlo simulation and sensitivity analysis to quantify the probable effect of individual risks on overall project schedule and cost objectives. It produces numerical probability distributions for project outcomes, supporting data-driven contingency decisions.

Concept tested: Quantitative Risk Analysis - numerical risk modeling

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Risk Management#Quantitative Risk Analysis#Project Objectives#PMBOK Processes

Community Discussion

No community discussion yet for this question.

Full CAPM Practice