A project manager is monitoring and recording results of executing the quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer…
The correct answer is B. Verified deliverables. This question tests knowledge of the outputs produced by the Control Quality process, specifically verified deliverables that confirm project outputs meet defined requirements.
Question
Options
- AApproved change requests
- BVerified deliverables
- CLessons learned
- DWork performance data
How the community answered
(39 responses)- B92% (36)
- C3% (1)
- D5% (2)
Why each option
This question tests knowledge of the outputs produced by the Control Quality process, specifically verified deliverables that confirm project outputs meet defined requirements.
Approved change requests are an output of the Perform Integrated Change Control process, not Control Quality.
Verified deliverables are a key output of the Control Quality process, produced after inspecting and measuring completed deliverables to confirm they are complete, correct, and comply with quality requirements. These verified deliverables then serve as an input to the Validate Scope process for formal stakeholder acceptance.
Lessons learned are captured in a lessons learned register, which is an output of many processes including Close Project or Phase, not specifically the monitoring of quality activities.
Work performance data is an input to Control Quality and other monitoring processes, capturing raw observations and measurements, not a primary output of the quality monitoring activity.
Concept tested: Control Quality process outputs - verified deliverables