CAPM · Question #103

CAPM Question #103: Real Exam Question with Answer & Explanation

The correct answer is B: Verified deliverables. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

A project manager is monitoring and recording results of executing the quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations. Which output is the project manager using?

Options

  • AApproved change requests
  • BVerified deliverables
  • CLessons learned
  • DWork performance data

Topics

#Quality Management#Control Quality#Verified Deliverables#Project Outputs