PMIPMI
CAPM · Question #10
CAPM Question #10: Real Exam Question with Answer & Explanation
The correct answer is B: 15 days. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
The project manager has the following information about the estimated duration for an activity: - Most likely [tM] " 15 days - Pessimistic [tP] " 20 days - Optimistic [tO] " 10 days What is the estimated duration of this activity, according to the triangular distribution technique?
Options
- A10 days
- B15 days
- C12.5 days
- D5 days
Topics
#Activity Duration Estimating#Triangular Distribution#Three-Point Estimating
Community Discussion
No community discussion yet for this question.