nerdexam
PMIPMI

CAPM · Question #10

CAPM Question #10: Real Exam Question with Answer & Explanation

The correct answer is B: 15 days. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

The project manager has the following information about the estimated duration for an activity: - Most likely [tM] " 15 days - Pessimistic [tP] " 20 days - Optimistic [tO] " 10 days What is the estimated duration of this activity, according to the triangular distribution technique?

Options

  • A10 days
  • B15 days
  • C12.5 days
  • D5 days

Topics

#Activity Duration Estimating#Triangular Distribution#Three-Point Estimating

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions