Which of the following is visible in the project planning board? Note: There are 2 correct answers to this question

The correct answer is B. Capacity requirements C. Maintenance orders assigned to an activity. The project planning board is a graphical tool that allows you to plan and monitor projects in a Gantt chart view. You can use the project planning board to display capacity requirements and maintenance orders that are related to project activities. You can also display other…

Project Planning

Question

Which of the following is visible in the project planning board? Note: There are 2 correct answers to this question

Options

  • AProject-relevant purchase orders
  • BCapacity requirements
  • CMaintenance orders assigned to an activity
  • DProduction orders assigned to WBS elements

How the community answered

(23 responses)
  • A
    4% (1)
  • B
    91% (21)
  • D
    4% (1)

Explanation

The project planning board is a graphical tool that allows you to plan and monitor projects in a Gantt chart view. You can use the project planning board to display capacity requirements and maintenance orders that are related to project activities. You can also display other objects such as WBS elements, networks, activities, milestones, production orders, sales orders, purchase orders, and so on.

Topics

#project planning board#capacity requirements#maintenance orders#Gantt chart