C_TS412_2021 · Question #22

To which object can you assign a factory calendar?

The correct answer is B. Network header. To assign a factory calendar, you can use the network header. The network header is a structural element of a network that contains general data and settings for a network, such as its order type, number range, scheduling parameters, and so on. The network header also contains…

Project Planning

Question

To which object can you assign a factory calendar?

Options

  • AMaterial component
  • BNetwork header
  • CRelationship
  • DMilestone

How the community answered

(31 responses)
  • A
    6% (2)
  • B
    87% (27)
  • C
    3% (1)
  • D
    3% (1)

Explanation

To assign a factory calendar, you can use the network header. The network header is a structural element of a network that contains general data and settings for a network, such as its order type, number range, scheduling parameters, and so on. The network header also contains the factory calendar field, which allows you to assign a factory calendar to a network. A factory calendar is a parameter that defines the working days and holidays for a plant or a location. A factory calendar is used to determine the dates and durations of activities and networks based on their workdays and non-workdays.

Topics

#factory calendar#network header#scheduling#configuration