C_TS412_2021 · Question #114
Which sets of dates can be used to schedule networks? Note: There are 2 correct answers to this question
The correct answer is A. Basic dates D. Planned dates. Basic dates and planned dates are some of the sets of dates that can be used to schedule networks. Basic dates are the earliest possible start and finish dates of an activity or a network, based on its dependencies and constraints. Planned dates are the scheduled start and…
Question
Which sets of dates can be used to schedule networks? Note: There are 2 correct answers to this question
Options
- ABasic dates
- BForecast dates
- CBaseline dates
- DPlanned dates
How the community answered
(48 responses)- A92% (44)
- B2% (1)
- C6% (3)
Explanation
Basic dates and planned dates are some of the sets of dates that can be used to schedule networks. Basic dates are the earliest possible start and finish dates of an activity or a network, based on its dependencies and constraints. Planned dates are the scheduled start and finish dates of an activity or a network, based on its basic dates and available capacities.
Topics
Community Discussion
No community discussion yet for this question.