nerdexam
SAP

C_TS412_2021 · Question #11

In your logistics project you want to carry out the internal project work as soon as possible. What do you have to maintain in capacity requirements planning?

The correct answer is C. Control key of an activity. To carry out the internal project work as soon as possible, you have to maintain the control key of an activity in capacity requirements planning. Capacity requirements planning is a process that determines the capacity requirements and availability for work centers or…

Project Planning

Question

In your logistics project you want to carry out the internal project work as soon as possible. What do you have to maintain in capacity requirements planning?

Options

  • AScheduling and capacity category
  • BScheduling and distribution key
  • CControl key of an activity
  • DCapacity planner group in the network header

How the community answered

(42 responses)
  • A
    5% (2)
  • B
    2% (1)
  • C
    81% (34)
  • D
    12% (5)

Explanation

To carry out the internal project work as soon as possible, you have to maintain the control key of an activity in capacity requirements planning. Capacity requirements planning is a process that determines the capacity requirements and availability for work centers or resources that are used to execute project activities. The control key is a parameter that defines the basic properties of an activity, such as whether it is internally or externally processed, whether it requires confirmation or not, and whether it is relevant for scheduling or not. The control key also determines whether an activity is relevant for capacity requirements planning or not. To carry out the internal project work as soon as possible, you have to use a control key that activates capacity requirements planning for the internal activities.

Topics

#capacity planning#control key#network activity#scheduling

Community Discussion

No community discussion yet for this question.

Full C_TS412_2021 Practice