C_TS412_2021 · Question #108
You want to extrapolate basic dates from lower to higher-level WBS elements. The duration of higher-level elements should NOT be reduced. Which planning method do you choose?
The correct answer is B. Strict bottom-up. Strict bottom-up planning rolls up dates without reducing the duration of higher-level WBS
Project Planning
Question
You want to extrapolate basic dates from lower to higher-level WBS elements. The duration of higher-level elements should NOT be reduced. Which planning method do you choose?
Options
- ABottom-up
- BStrict bottom-up
- CFree planning
- DTop-down
How the community answered
(25 responses)- A4% (1)
- B88% (22)
- D8% (2)
Explanation
Strict bottom-up planning rolls up dates without reducing the duration of higher-level WBS
Topics
#strict bottom-up planning#basic dates#WBS date extrapolation#date planning methods