C_TS412_2021 · Question #108

You want to extrapolate basic dates from lower to higher-level WBS elements. The duration of higher-level elements should NOT be reduced. Which planning method do you choose?

The correct answer is B. Strict bottom-up. Strict bottom-up planning rolls up dates without reducing the duration of higher-level WBS

Project Planning

Question

You want to extrapolate basic dates from lower to higher-level WBS elements. The duration of higher-level elements should NOT be reduced. Which planning method do you choose?

Options

  • ABottom-up
  • BStrict bottom-up
  • CFree planning
  • DTop-down

How the community answered

(25 responses)
  • A
    4% (1)
  • B
    88% (22)
  • D
    8% (2)

Explanation

Strict bottom-up planning rolls up dates without reducing the duration of higher-level WBS

Topics

#strict bottom-up planning#basic dates#WBS date extrapolation#date planning methods