C_TS412_2021 · Question #106

A customer project must be finished at a given due date. The project consists of WBS elements and networks. What scheduling type do you use?

The correct answer is D. Backward. To schedule a project that must be finished at a given due date, you should use backward scheduling. Backward scheduling is a type of scheduling that calculates the dates of project objects, such as WBS elements and networks, based on their dependencies and constraints…

Project Planning

Question

A customer project must be finished at a given due date. The project consists of WBS elements and networks. What scheduling type do you use?

Options

  • AOnly capacity requirements
  • BForward
  • CCurrent date
  • DBackward

How the community answered

(39 responses)
  • A
    8% (3)
  • B
    3% (1)
  • C
    3% (1)
  • D
    87% (34)

Explanation

To schedule a project that must be finished at a given due date, you should use backward scheduling. Backward scheduling is a type of scheduling that calculates the dates of project objects, such as WBS elements and networks, based on their dependencies and constraints, starting from a fixed end date and working backwards. Backward scheduling ensures that the project is completed by the due date and that any delays are identified as early as possible.

Topics

#backward scheduling#scheduling type#WBS scheduling#network scheduling