C_TS412_2021 · Question #106
A customer project must be finished at a given due date. The project consists of WBS elements and networks. What scheduling type do you use?
The correct answer is D. Backward. To schedule a project that must be finished at a given due date, you should use backward scheduling. Backward scheduling is a type of scheduling that calculates the dates of project objects, such as WBS elements and networks, based on their dependencies and constraints…
Question
A customer project must be finished at a given due date. The project consists of WBS elements and networks. What scheduling type do you use?
Options
- AOnly capacity requirements
- BForward
- CCurrent date
- DBackward
How the community answered
(39 responses)- A8% (3)
- B3% (1)
- C3% (1)
- D87% (34)
Explanation
To schedule a project that must be finished at a given due date, you should use backward scheduling. Backward scheduling is a type of scheduling that calculates the dates of project objects, such as WBS elements and networks, based on their dependencies and constraints, starting from a fixed end date and working backwards. Backward scheduling ensures that the project is completed by the due date and that any delays are identified as early as possible.