810-440 · Question #206

Which two options are part of the five steps approach needed to conduct a stakeholder analysis? (Choose two.)

The correct answer is A. Define ways to move stakeholders from their current to future position. B. Identify customer stakeholders.. Two key steps in conducting a stakeholder analysis involve first identifying all relevant customer stakeholders and then defining strategies to transition them from their current stance to a desired future position regarding the project or initiative.

Executing the Business Architecture Approach

Question

Which two options are part of the five steps approach needed to conduct a stakeholder analysis? (Choose two.)

Options

  • ADefine ways to move stakeholders from their current to future position.
  • BIdentify customer stakeholders.
  • CDefine absolute power and interest of stakeholders.
  • DGenerate consensus among stakeholders.

How the community answered

(21 responses)
  • A
    86% (18)
  • C
    5% (1)
  • D
    10% (2)

Why each option

Two key steps in conducting a stakeholder analysis involve first identifying all relevant customer stakeholders and then defining strategies to transition them from their current stance to a desired future position regarding the project or initiative.

ADefine ways to move stakeholders from their current to future position.Correct

Defining ways to move stakeholders from their current to a future position is a critical step in stakeholder analysis, as it involves strategizing how to influence, engage, and gain support from stakeholders to align with project goals. This involves developing specific actions to address their concerns and leverage their support.

BIdentify customer stakeholders.Correct

Identifying customer stakeholders is the foundational first step of any stakeholder analysis, as it requires recognizing all individuals or groups who are impacted by, or can impact, the project, ensuring no critical party is overlooked. This initial mapping is essential before any further analysis or strategy development can occur.

CDefine absolute power and interest of stakeholders.

Stakeholder analysis typically involves defining power and interest (often categorized as high/low or on a matrix) but rarely aims to define 'absolute' power and interest, as influence can be dynamic and relative.

DGenerate consensus among stakeholders.

While generating consensus can be a goal of stakeholder management, it is often an outcome of effective engagement strategies developed during and after a stakeholder analysis, rather than a distinct step within the analysis itself.

Concept tested: Steps in stakeholder analysis

Topics

#stakeholder analysis#stakeholder management#project management steps