810-440 · Question #207
Which two factors must you know about stakeholders to identify where they fall in a power grid? (Choose two.)
The correct answer is C. degree of interest E. degree of influence. To position stakeholders accurately on a power-interest grid, it is essential to understand their level of interest in the project and their overall degree of influence over its outcomes.
Question
Which two factors must you know about stakeholders to identify where they fall in a power grid? (Choose two.)
Options
- Arole in company
- Bpurchasing power
- Cdegree of interest
- Dsize of budget
- Edegree of influence
How the community answered
(31 responses)- A3% (1)
- B3% (1)
- C94% (29)
Why each option
To position stakeholders accurately on a power-interest grid, it is essential to understand their level of interest in the project and their overall degree of influence over its outcomes.
While a stakeholder's role in the company might correlate with influence or interest, it is not a direct axis for the power-interest grid itself.
Purchasing power is a financial metric related to a stakeholder's ability to buy, but it is not a direct factor used to plot stakeholders on a power-interest grid.
The degree of interest is a critical axis on the power-interest grid, indicating how much a stakeholder cares about the project's success or failure, which dictates whether they need to be kept informed or engaged.
Size of budget is a financial attribute and not a direct dimension used to determine a stakeholder's position on a power-interest grid.
The degree of influence is the other crucial axis on the power-interest grid, representing a stakeholder's ability to impact project decisions or outcomes, determining if they need to be managed closely or merely monitored.
Concept tested: Stakeholder power-interest grid analysis