Question

You are managing a project by using Project Professional 2013, and you notice a potential scheduling problem indicated by wavy red lines under some of the dates in the Finish column. You need to resolve the issue. What should you do?

Options

  • ARecalculate the project schedule.
  • BAdjust the resource assignment on the task to when the resource is available.
  • CActivate Task Inspector for the task to decide if adjustments are necessary.
  • DAdjust the finish date on the task to a date in the future.