Question
You are managing a project by using Project Professional 2013, and you notice a potential scheduling problem indicated by wavy red lines under some of the dates in the Finish column. You need to resolve the issue. What should you do?
Options
- ARecalculate the project schedule.
- BAdjust the resource assignment on the task to when the resource is available.
- CActivate Task Inspector for the task to decide if adjustments are necessary.
- DAdjust the finish date on the task to a date in the future.
Community Discussion
No community discussion yet for this question.