You use Project Professional 2013 to manage a project for your organization. You are tracking work in a project which contains a baseline and resource assignments. You want to view the work variance…
The correct answer is D. View the Task Usage view and insert the Work Variance column on the left side of the view. See the full explanation below for the reasoning.
Question
You use Project Professional 2013 to manage a project for your organization. You are tracking work in a project which contains a baseline and resource assignments. You want to view the work variance for a specific resource for a specific task. You need to choose a view that will show this information. What should you do?
Options
- AView the Resource Sheet that shows the Work table.
- BView the Gantt chart in split view with Task form formatted to show Work Details.
- CView the Resource Sheet view and insert the Work Variance field.
- DView the Task Usage view and insert the Work Variance column on the left side of the view.
How the community answered
(57 responses)- A5% (3)
- B4% (2)
- C11% (6)
- D81% (46)