74-343 · Question #83

You manage a project by using Project Professional 2013. The Indicators column in the Gantt Chart view shows that there are overallocated resources for a task. A resource is assigned to multiple…

The correct answer is B. A Finish to Start relationship. See the full explanation below for the reasoning.

Question

You manage a project by using Project Professional 2013. The Indicators column in the Gantt Chart view shows that there are overallocated resources for a task. A resource is assigned to multiple tasks at 100% on a specific day, totaling 2.5 hours of work for the day. The resource has availability of 8 hours for the day. You need to solve this problem. What should you add to the task?

Options

  • AA deadline
  • BA Finish to Start relationship
  • CA Finish to Finish relationship
  • DMore work

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    71% (20)
  • C
    18% (5)
  • D
    7% (2)