Microsoft
74-343 · Question #83
74-343 Question #83: Real Exam Question with Answer & Explanation
Sign in or unlock 74-343 to reveal the answer and full explanation for question #83. The question stem and answer options stay visible for context.
Question
You manage a project by using Project Professional 2013. The Indicators column in the Gantt Chart view shows that there are overallocated resources for a task. A resource is assigned to multiple tasks at 100% on a specific day, totaling 2.5 hours of work for the day. The resource has availability of 8 hours for the day. You need to solve this problem. What should you add to the task?
Options
- AA deadline
- BA Finish to Start relationship
- CA Finish to Finish relationship
- DMore work
Unlock 74-343 to see the answer
You've previewed enough free 74-343 questions. Unlock 74-343 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.