74-343 · Question #83
You manage a project by using Project Professional 2013. The Indicators column in the Gantt Chart view shows that there are overallocated resources for a task. A resource is assigned to multiple…
The correct answer is B. A Finish to Start relationship. See the full explanation below for the reasoning.
Question
You manage a project by using Project Professional 2013. The Indicators column in the Gantt Chart view shows that there are overallocated resources for a task. A resource is assigned to multiple tasks at 100% on a specific day, totaling 2.5 hours of work for the day. The resource has availability of 8 hours for the day. You need to solve this problem. What should you add to the task?
Options
- AA deadline
- BA Finish to Start relationship
- CA Finish to Finish relationship
- DMore work
How the community answered
(28 responses)- A4% (1)
- B71% (20)
- C18% (5)
- D7% (2)