Microsoft
74-343 · Question #82
Your project managers manage several projects using Project Professional 2013. Each individual project contains a saved baseline. You need to capture in the master project the baseline data from the…
The correct answer is D. Create a Master project and insert all of the individual projects with an update link. See the full explanation below for the reasoning.
Question
Your project managers manage several projects using Project Professional 2013. Each individual project contains a saved baseline. You need to capture in the master project the baseline data from the member projects at the summary levels for reporting purposes. What should you do?
Options
- ACreate a Master project and insert all of the individual projects without an update link.
- BOpen all of the projects and create a New Window view.
- CTurn on the option Inserted projects are calculated like summary tasks.
- DCreate a Master project and insert all of the individual projects with an update link.
How the community answered
(28 responses)- A4% (1)
- B11% (3)
- C4% (1)
- D82% (23)
Community Discussion
No community discussion yet for this question.