Question
Your project managers manage several projects using Project Professional 2013. Each individual project contains a saved baseline. You need to capture in the master project the baseline data from the member projects at the summary levels for reporting purposes. What should you do?
Options
- ACreate a Master project and insert all of the individual projects without an update link.
- BOpen all of the projects and create a New Window view.
- CTurn on the option Inserted projects are calculated like summary tasks.
- DCreate a Master project and insert all of the individual projects with an update link.
Unlock 74-343 to see the answer