Question

While scheduling with Project Professional 2013 you notice that there are three days of remaining duration on the Database Design task. The resource performing this task indicates that the work is completed. You need to update the schedule to reflect this change. What should you do?

Options

  • AEnter a status date for the task.
  • BEnter 0 in remaining duration.
  • CReschedule uncompleted work for the project schedule.
  • DClick on the task, and then click 100% complete.