74-343 · Question #80

You manage a project schedule by using Project Professional 2013. You are concerned about project costs. After viewing the Cost Variance column, you realize that the project has a cost variance of…

The correct answer is D. View the Cost Overrun report. See the full explanation below for the reasoning.

Question

You manage a project schedule by using Project Professional 2013. You are concerned about project costs. After viewing the Cost Variance column, you realize that the project has a cost variance of 55,000.00. You need to view graphically which tasks and resources are causing the $5,000.00 cost variance. What should you do?

Options

  • AView the Resource Graph's Cumulative Cost view.
  • BView the Task Cost Overview report.
  • CView the Over Budget Tasks report.
  • DView the Cost Overrun report.

How the community answered

(49 responses)
  • A
    4% (2)
  • B
    10% (5)
  • C
    4% (2)
  • D
    82% (40)