74-343 · Question #80
You manage a project schedule by using Project Professional 2013. You are concerned about project costs. After viewing the Cost Variance column, you realize that the project has a cost variance of…
The correct answer is D. View the Cost Overrun report. See the full explanation below for the reasoning.
Question
You manage a project schedule by using Project Professional 2013. You are concerned about project costs. After viewing the Cost Variance column, you realize that the project has a cost variance of 55,000.00. You need to view graphically which tasks and resources are causing the $5,000.00 cost variance. What should you do?
Options
- AView the Resource Graph's Cumulative Cost view.
- BView the Task Cost Overview report.
- CView the Over Budget Tasks report.
- DView the Cost Overrun report.
How the community answered
(49 responses)- A4% (2)
- B10% (5)
- C4% (2)
- D82% (40)