Question
You are a project manager for a company that uses baselines in Project Standard 2013. Project stakeholders approve an update to the baseline of a project in progress. You enter the new tasks necessary to include the project schedule changes. You need to update the baseline for the new tasks. What should you do?
Options
- ADelete the current baseline and re-baseline the entire project.
- BCopy the current schedule to the baseline1 fields.
- CSelect the new tasks and copy the schedule to the baseline1 fields for the selected tasks.
- DSelect the new tasks and set the baseline for the selected tasks.