Microsoft
74-343 · Question #78
74-343 Question #78: Real Exam Question with Answer & Explanation
Sign in or unlock 74-343 to reveal the answer and full explanation for question #78. The question stem and answer options stay visible for context.
Question
You are a project manager who uses Project Standard 2013. You manage a large project and are capturing actual work for the tasks as they are being worked. You do not need to enter the time on the actual day worked; however, you need to capture the total amount of time spent on the task. The fixed work task has a baseline of 20 hours, and the developer's timecard displays the following hours: Monday = 2 hours Tuesday = 8 hours Wednesday = 4 hours Thursday = 2 hours Friday = 2 hours The developer informs you that the task is now complete. You need to update the actual work and mark the task complete. What should you do?
Options
- AOpen the Task Form and format it to show Work Details.
- BOpen the Task Form and format it to show Schedule Details.
- COpen the Task Form and format it to show Work Details.
- DOpen the Task Form and format it to show Schedule View.
Unlock 74-343 to see the answer
You've previewed enough free 74-343 questions. Unlock 74-343 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.