74-343 · Question #78

You are a project manager who uses Project Standard 2013. You manage a large project and are capturing actual work for the tasks as they are being worked. You do not need to enter the time on the…

The correct answer is C. Open the Task Form and format it to show Work Details. See the full explanation below for the reasoning.

Question

You are a project manager who uses Project Standard 2013. You manage a large project and are capturing actual work for the tasks as they are being worked. You do not need to enter the time on the actual day worked; however, you need to capture the total amount of time spent on the task. The fixed work task has a baseline of 20 hours, and the developer's timecard displays the following hours:

Monday = 2 hours Tuesday = 8 hours Wednesday = 4 hours Thursday = 2 hours Friday = 2 hours The developer informs you that the task is now complete. You need to update the actual work and mark the task complete. What should you do?

Options

  • AOpen the Task Form and format it to show Work Details.
  • BOpen the Task Form and format it to show Schedule Details.
  • COpen the Task Form and format it to show Work Details.
  • DOpen the Task Form and format it to show Schedule View.

How the community answered

(56 responses)
  • A
    2% (1)
  • B
    9% (5)
  • C
    84% (47)
  • D
    5% (3)

Community Discussion

No community discussion yet for this question.