Microsoft
74-343 · Question #75
You are a project manager who uses Project Professional 2013. You need to change the default for all new projects so that tasks will be created in Auto Scheduled mode. What should you do?
The correct answer is E. Set the New tasks created option to Auto Scheduled and set the Schedule Options to All. See the full explanation below for the reasoning.
Question
You are a project manager who uses Project Professional 2013. You need to change the default for all new projects so that tasks will be created in Auto Scheduled mode. What should you do?
Options
- AFor each new project, use the Status Bar to set new tasks to be auto scheduled.
- BFor each new project, use the Auto Schedule button on the Tasks tab.
- COpen the Global.mpt and use the Auto Schedule button on the Tasks tab.
- DSet the Default task type to Auto Scheduled for All New Projects in the Schedule Options.
- ESet the New tasks created option to Auto Scheduled and set the Schedule Options to All
How the community answered
(65 responses)- A9% (6)
- B6% (4)
- C2% (1)
- D3% (2)
- E80% (52)
Community Discussion