You are using Microsoft Project Professional 2013. Three years ago, you successfully completed a project to review all of the suppliers within your organization, and you have been asked to run a…

The correct answer is D. Use the New from existing project option to create the new project. See the full explanation below for the reasoning.

Question

You are using Microsoft Project Professional 2013. Three years ago, you successfully completed a project to review all of the suppliers within your organization, and you have been asked to run a similar project again. You still have the project plan from three years ago. You need to use the most efficient method to produce a new plan with tasks based upon the old project plan. What should you do?

Options

  • ARename the old plan to a .mpt file, and select it from the featured templates to create the
  • BOpen the file in an earlier version of Project Professional and save it as a Project
  • COpen the file, and copy and paste the task list into the schedule.
  • DUse the New from existing project option to create the new project.

How the community answered

(26 responses)
  • A
    4% (1)
  • B
    15% (4)
  • C
    4% (1)
  • D
    77% (20)

Community Discussion

No community discussion yet for this question.

Full 74-343 Practice