You are a project manager who uses Project Professional 2013. A customer has sent you a project plan, which contains several custom fields that you want to use in your project. You have a custom…
The correct answer is D. Open the custom fields dialog box and use the Import Fields button. See the full explanation below for the reasoning.
Question
You are a project manager who uses Project Professional 2013. A customer has sent you a project plan, which contains several custom fields that you want to use in your project. You have a custom field named CF1 in the Number1 field in your project, and you have a custom field named CF2 in the Number1 field of your customer's project. You need to copy the custom fields from your customer's project into your own. You do not want to overwrite your project custom field. You open both projects. What should you do next?
Options
- AUse the Organizer to move the custom fields from one project to the other.
- BCut and paste the custom fields from one project to the other.
- CDrag the custom fields from one project to the other.
- DOpen the custom fields dialog box and use the Import Fields button.
How the community answered
(27 responses)- A4% (1)
- B19% (5)
- C7% (2)
- D70% (19)