Question
You are a project manager who uses Project Standard 2013. A colleague sends you a Microsoft Excel file that contains a list of tasks that define a project you must complete. You need to create a project file that contains this task list, ensuring that any fields are mapped correctly. What should you do?
Options
- AAdd the Import Project Wizard to the Quick Access Toolbar.
- BOpen the file in Excel, and copy and paste the tasks into a new project.
- CRename the Excel file to tasks.mpp and open the plan in Project Standard 2013.
- DOpen the Excel file by using Project Standard 2013 and import the task list using the Project