nerdexam
Microsoft

74-343 · Question #73

74-343 Question #73: Real Exam Question with Answer & Explanation

The correct answer is D. Open the Excel file by using Project Standard 2013 and import the task list using the Project. See the full explanation below for the reasoning.

Question

You are a project manager who uses Project Standard 2013. A colleague sends you a Microsoft Excel file that contains a list of tasks that define a project you must complete. You need to create a project file that contains this task list, ensuring that any fields are mapped correctly. What should you do?

Options

  • AAdd the Import Project Wizard to the Quick Access Toolbar.
  • BOpen the file in Excel, and copy and paste the tasks into a new project.
  • CRename the Excel file to tasks.mpp and open the plan in Project Standard 2013.
  • DOpen the Excel file by using Project Standard 2013 and import the task list using the Project

Community Discussion

No community discussion yet for this question.

Full 74-343 Practice