You are a project manager who uses Project Professional 2013. You are planning an office move, which will occur over a weekend. You use Auto Scheduled tasks and create a weekend working calendar…

The correct answer is C. Assign the task calendar to the task using the Task Information dialog box. See the full explanation below for the reasoning.

Question

You are a project manager who uses Project Professional 2013. You are planning an office move, which will occur over a weekend. You use Auto Scheduled tasks and create a weekend working calendar. You need to assign the weekend working calendar to the task. What should you do?

Options

  • AChange the start date of the task to the Saturday, which will assign the weekend working
  • BClick on the Task tab and select the Change Working Time button.
  • CAssign the task calendar to the task using the Task Information dialog box.
  • DRight-click on the weekend on the Gantt chart and select the weekend working calendar.

How the community answered

(40 responses)
  • A
    5% (2)
  • B
    3% (1)
  • C
    80% (32)
  • D
    13% (5)