Question
You are a project manager who uses Project Standard 2013. Your current project has resources with the standard calendar as the base calendar. Some tasks of the project need to be done overnight so the night shift calendar is assigned to those tasks. When you assign a resource to one of these tasks, you get an error. You need to correctly assign the resource. What should you do?
Options
- ARemove the night calendar from the task and re-assign the resource.
- BChange the task mode to Manually Scheduled.
- CChange the task type to Fixed Units, Effort Driven, and then re-assign the resource.
- DSelect scheduling ignores resource calendars for the task.