You are using Project Standard 2013. You want the ability to see only tasks that have finish dates past their deadline date You need to achieve this goal using a custom field. What should you do?

The correct answer is B. Use the Task Flagl5 custom field. See the full explanation below for the reasoning.

Question

You are using Project Standard 2013. You want the ability to see only tasks that have finish dates past their deadline date You need to achieve this goal using a custom field. What should you do?

Options

  • ACreate a Lookup containing the values Yes and No against the Task Text1 custom field.
  • BUse the Task Flagl5 custom field.
  • CUse the Task Text30 custom field, also known as the Deadline Flag, since it automatically
  • DRename the Task Number1 custom field to Deadline passed.

How the community answered

(43 responses)
  • A
    7% (3)
  • B
    72% (31)
  • C
    5% (2)
  • D
    16% (7)